The first phase of construction including earthworks, the production of the foundation slab, the erection of the central service core and the technical room has been completed on schedule in October. During winter the wooden walls will be produced customized by CNC-cutting. In spring the framing will be finalized by setting up the prefabricated large-format solid timber elements and the roof. The interior finish will be completed till autumn 2015. A local general contractor carries out all masons’ works and is responsible for the coordination and building supervision.